The first job for Sherpa2 was a day on the shop floor at The Somerset Grill Co, testing the fractional Continuous Improvement idea for real. Working alongside their team, not sitting in a meeting room.

I’d already trained some of this team in business improvement, so some of what we found wasn’t a total surprise to them. Even so, we walked away with 38 separate improvement actions. More than half hadn’t been on anyone’s radar.

What we found

  • Build schedule. Nobody could see tomorrow’s build, so sub assembly parts were being made too early.

  • A hidden bottleneck. A known bottleneck machine turned out to have one side that was barely being used.

  • SOPs missing detail. Standard operating procedures were in place, but they lacked the detail that makes them useful, like bolt identifiers and the correct assembly order.

Theory isn’t the same as seeing it

That’s usually how it goes. Even with a team who already gets the theory, knowing the principles and seeing them play out on your own shop floor are two different things. Someone still needs to stand in it for a full day to join the dots.

And I loved it.

Today that first day is called a Tester Day. One day on your shop floor, a prioritised list of improvements, and if I don’t find savings worth more than the £995 fee, you don’t pay.

If you know your South West business could be more efficient, I’d be happy to have a conversation.